Flat rack
A platform with walls only at the ends, or none at all. It allows loading from the sides and from above, and accepts pieces wider than the container. Available in 20' and 40'.
Services · 04 / Project cargo
When the equipment does not fit in a container, transport stops being a rate and becomes a project. The route has to be measured before moving it, permits obtained, cranes coordinated and the bridge checked to see whether it will hold.
We handle it from preliminary engineering to delivery on site.
What project cargo is
A shipment enters this territory when at least one of these things happens.
Ocean mode
It is the only one with no practical weight ceiling and the one that offers the most equipment alternatives.
A platform with walls only at the ends, or none at all. It allows loading from the sides and from above, and accepts pieces wider than the container. Available in 20' and 40'.
A conventional container without a rigid roof, closed with a tarpaulin. It works when the piece exceeds the height but not the width, and when it has to be loaded by crane from above.
The cargo travels loose in the vessel’s hold, without a container. It is used when the piece is so large that no combination of open equipment works. It requires a stowage plan, calculated lashing and often a general cargo vessel, with lower frequencies than container ships.
Roll on, roll off: the vessel has a ramp and the cargo enters rolling. It is the natural option for self-propelled machinery. When the equipment cannot move on its own, it can be shipped on a rolling platform, avoiding the lift.
What sticks out is called out-of-gauge, or OOG. The shipping line charges according to how much sticks out and in which direction, because that determines how many stowage spaces are blocked around it: a piece that sticks out twenty centimeters on each side can cost as if it took up three containers, because the shipping line cannot put anything next to it.
Ocean considerations
Air mode
It makes sense when the cost of having the site stopped exceeds any freight: a critical component of a stopped plant can fly, even if the freight costs several times what the piece does.
What limits it
Air considerations
Road mode
Even if it has crossed the ocean. And it is the leg where things get most complicated.
Permits
In Chile, transport that exceeds the permitted dimensions or weight requires authorization from the road authority. The permit defines the exact route, the hours and whether an escort is needed.
It is not an automatic process. The proposed route is assessed: the bridges the cargo will cross, the clearances of the underpasses, the turning radii on the curves.
Route survey
It is what distinguishes project transport from normal freight, and it is done before committing to the operation: physically travelling the road and measuring every restriction, from the clearance under each bridge and cable to the gradient on the access roads.
When an insurmountable obstacle appears there are three ways out: change the route, dismantle the piece at origin, or intervene on the obstacle. Finding that problem in the survey costs time. Finding it with the truck stopped halfway costs much more.
Equipment
A reduced-height platform that gains centimeters of clearance. It is the base equipment for machinery.
It lengthens for long pieces that cannot take an overhang.
Platforms that couple together and adjust their height independently. They are used for high-tonnage loads and allow the weight to be spread over more axles, which is what makes crossing a bridge viable.
Road considerations
How we operate
You can follow your cargo on the MyDucis portal once the shipment is confirmed.
Before quoting
With that we can say whether it is viable and how much it costs. Without it, any number is a guess.
Next step
With the drawing or the technical data sheet we can say whether it is viable and on what timeline. If information is missing, we write to you before quoting instead of giving you a number that changes later.